The team portal

97.2% of it built.

Running every day. It is the back office we work in, not a product we sell, and what we learned building it is what we build client back offices with.

Building25 of 27 shippedHow it was built

Read from the copy of the company plan written Oct 10, 2026, 5:00 a.m.. The live plan has not answered yet.

Shipped this week

Timeline

Every dated piece and the dates the project works to, as the plan says now, beside what the plan of 7 October said.

  1. Shipped

    A map of every machine

    Done September 17, 2026

  2. Shipped

    An allow-list for signing in

    Done September 17, 2026

  3. Shipped

    An audit log sealed against editing

    Done September 17, 2026

  4. Shipped

    Documents and agreements signed in the portal

    Done September 17, 2026

  5. Shipped

    Interviews and scorecards

    Done September 17, 2026

  6. Shipped

    Offers and employment records

    Done September 17, 2026

  7. Shipped

    Roles and what each one may do

    Done September 17, 2026

  8. Shipped

    Scheduled jobs and their history

    Done September 17, 2026

  9. Shipped

    The status board

    Done September 17, 2026

  10. Shipped

    Time off and offboarding

    Done September 17, 2026

  11. Shipped

    Vacancies and applications

    Done September 17, 2026

  12. Shipped

    What the checks found, in one place

    Done September 17, 2026

  13. Shipped

    Human Resources in six screens, with help from an assistant

    Done October 7, 2026

  14. Shipped

    Support: one inbox, answers and response targets

    Done October 7, 2026

  15. Shipped

    Customers, deals and campaigns

    Done October 8, 2026

  16. Shipped

    Every page updates as things change

    Done October 8, 2026

  17. Shipped

    One place to sign every agreement

    Done October 8, 2026

  18. Shipped

    Our own double-entry books

    Done October 8, 2026

  19. Shipped

    Payouts and seats

    Done October 8, 2026

  20. Shipped

    Posts, a content calendar and the blog

    Done October 8, 2026

  21. Shipped

    Projects and the company plan

    Done October 8, 2026

  22. Shipped

    Sales and quotes

    Done October 8, 2026

  23. Shipped

    Tax and refunds

    Done October 8, 2026

  24. Shipped

    One page per product, with its feedback

    Done October 10, 2026

  25. Shipped

    Passkeys to approve the actions that matter

    Done October 10, 2026

  26. Today, October 10, 2026

    Release day, 15 October

    Planned for October 15, 2026, on plan

  27. Built

    Live sales and reconciliation for the opening

    Planned for October 19, 2026, added since 7 October

  28. Building

    The developer tools, in the same pattern

    Moved: planned for October 15, 2026, now October 28, 2026

  29. Release day, 30 October

    Planned for October 30, 2026, on plan

Modules